Recent contributions to heuristics for the Fm|prmu|Cmax and Fm|prmu|∑Cj problems
DOI:
https://doi.org/10.5281/zenodo.10101868Keywords:
Scheduling, Heuristics, Permutational Flow Shop, Makespan, Total Flow TimeAbstract
The permutation flow shop scheduling problem has been studied since 50s. Due to its NP-Hard complexity, several heuristics have been proposed for the problem, specially, for makespan and total flow time minimization. However, we verified the need to review the literature about the state-of-art that provide future directions for extensions, combinations and formulations for new heuristics. In this sense, this paper aims to review the literature of the Fm|prmu|Cmax and Fm|prmu|∑Cj problems. This paper classify the heuristics based on the frameworks proposed by Framinan et al. (2004) and Framinan et al. (2005) that classify the heuristics according to their composition (initial ordering, construction of the solution and improvement phase) and according to their labels (simple or composite). At least two future directions for the development of heuristics of high performance are highlighted: a) experimental studies evaluating the combination of the procedures proposed by the literature; b) proposition of new manners to develop the initial ordering, construction mechanisms and local searches exploring the existents gaps.
Downloads
References
Allahverdi, A.; Ng, C. T.; Cheng, T. E. & Kovalyov, M. Y. (2008). A survey of scheduling problems with setup times or costs. European Journal of Operational Research, v. 187, n. 3, p. 985–1032.
Allahverdi A & Aldowaisan T. (2002). New heuristics to minimize total completion time in m-machine flowshops. International Journal of Production Economics, v. 77, n. 1, p.71-83
Aydilek, H. & Allahverdi, A. (2012). Heuristics for no-wait flowshops with makespan subject to mean completion time. Applied Mathematics and Computation, v. 219, n. 1, 351-359.
Beightler, C. S.; Phillips, D. T. & Wilde, D. J. (1979). Foundations of optimization. 2. ed. Englewood Cliffs, NJ: Prentice-Hall.
Campbell, H. G.; Dudek, R. A. & Smith, M. L. (1970). Heuristic algorithm for n job, m machine sequencing problem. Management Science Series B-Application, v. 16, n. 1, p. 630-637.
Dannenbring, D. G. (1977). An evaluation of flow shop sequencing heuristics. Management Science, v. 23, n. 11, 1174-1182.
Dong, X.; Huang, H. & Chen, P. (2008) An improved NEH-based heuristic for the permutation flow shop problem. Computers & Operations Research, v. 35, n. 12, p. 3962-3968.
Elsayed, S. M.; Sarker, R. A. & Essam,D. L. (2014). A new genetic algorithm for solving optimization problems. Engineering Applications of Artificial Intelligence, v. 27, p. 57-69.
Fernandez-Viagas, V. & Framinan, J. M. (2014). On insertion tie-breaking rules in heuristics for the permutation flowshop scheduling problem. Computers & Operations Research, v. 45, p. 60-67.
Fernandez-Viagas, V. & Framinan, J. M. (2015). A new set of high-performing heuristics to minimise flowtime in permutation flowshops. Computers & Operations Research, v. 53, p. 68-80.
Framinan, J. M.; Gupta, J. N. & Leisten, R. (2004). A review and classification of heuristics for permutation flow-shop scheduling with makespan objective. Journal of the Operational Research Society, v. 55, n. 12, p. 1243-1255.
Framinan, J. M. & Leisten, R. (2003). An efficient constructive heuristic for flowtime minimisation in permutation flow shops. Omega, v. 31, n. 4, p. 311-317.
Framinan, J. M.; Leisten, R. & Ruiz-Usano, R. (2002). Efficient heuristics for flowshop sequencing with the objectives of makespan and flowtime minimisation. European Journal of Operational Research, v.141, n. 3, p. 559-569.
Framinan, J. M.; Leisten, R. & Ruiz-Usano, R. (2005). Comparison of heuristics for flowtime minimisation in permutation flowshops. Computers & Operations Research, v. 32, n. 5, p. 1237-1254.
Gao, S., Liu, Y.; Zhang, W. & Zhang, J. (2007, July). Some supplementation for NEH heuristic in solving flow shop problem. In American Control Conference, 2007. ACC’07 (pp. 3348-3352). IEEE.
Garey, M. R.; Johnson, D. S. & Sethi, R. (1976). The complexity of flowshop and jobshop scheduling. Mathematics of Operations Research, v. 1, n. 2, p. 117-129.
Gonzalez, T. & Sahni, S. (1978). Flowshop and jobshop schedules: complexity and approximation. Operations Research, v. 26, n. 1, p. 36-52.
Graham, R. L.; Lawler, E. L.; Lenstra, J. K. & Kan, A. R. (1979). Optimization and approximation in deterministic sequencing and scheduling: a survey. Annals of Discrete Mathematics, v. 5, p. 287-326.
Gupta, J. N. (1971). A functional heuristic algorithm for the flowshop scheduling problem. Operational Research Quarterly, v. 22, n. 1, p. 39-47.
Gupta, J. N. & Stafford, E. F. (2006). Flowshop scheduling research after five decades. European Journal of Operational Research, v. 169, n. 3, p. 699-711.
Hejazi, S.; R. & Saghafian, S. (2005). Flowshop-scheduling problems with makespan criterion: a review. International Journal of Production Research, v. 43, n. 14, p. 2895-2929.
Hundal, T. S. & Rajgopal, J. (1988). An extension of Palmer’s heuristic for the flow shop scheduling problem. The International Journal of Production Research, v. 26, n.6, p. 1119-1124.
Johnson, S. M. (1954). Optimal two‐and three‐stage production schedules with setup times included. Naval research logistics quarterly, v. 1, n. 1, p. 61-68.
Kalczynski, P. J. & Kamburowski, J. (2007). On the NEH heuristic for minimizing the makespan in permutation flow shops. Omega, v. 35, n. 1, p. 53-60.
Kalczynski, P. J. & Kamburowski, J. (2008). An improved NEH heuristic to minimize makespan in permutation flow shops. Computers & Operations Research, v. 35. n. 9, p. 3001-3008.
Kalczynski, P. J. & Kamburowski, J. (2009). An empirical analysis of the optimality rate of flow shop heuristics. European Journal of Operational Research, v. 198, n. 1, p. 93-101.
Kalczynski, P. J. & Kamburowski, J. (2011). On recent modifications and extensions of the NEH heuristic for flow shop sequencing. Foundations of Computing and Decision Sciences, v. 36, n. 1, p. 17-34.
Koulamas, C. (1998). A new constructive heuristic for the flowshop scheduling problem. European Journal of Operational Research, v. 105, n. 1, p. 66-71.
Laha, D. & Sarin, S. C. (2009). A heuristic to minimize total flow time in permutation flow shop. Omega, v. 37, n. 3, p. 734-739.
Liu, J. & Reeves, C. R. (2001). Constructive and composite heuristic solutions to the P||∑ Cj scheduling problem. European Journal of Operational Research, v. 132, n. 2, p. 439-452.
Li, X. & Wang, Q. (2006). Iterative heuristics for permutation flow shops with total flowtime minimization. In: Shen W, editor. Information technology for balanced manufacturing systems. IFIP TC5. Proceedings of the WG 5.5 seventh international conference on information technology for balanced automation systems in manufacturing and services. New York: Springer US, p. 349-56, 2006.
Li, X.; Wang, Q., & Wu, C. (2009). Efficient composite heuristics for total flowtime minimization in permutation flow shops. Omega, v. 37, n. 1, p. 155-164.
Low, C.; Yeh, J. Y. & Huang, K. I. (2004). A robust simulated annealing heuristic for flow shop scheduling problems. The International Journal of Advanced Manufacturing Technology, v. 23, n. 9-10, p. 762-767.
MacCarthy, B. L. & Liu, J. (1993). Addressing the gap in scheduling research: a review of optimization and heuristic methods in production scheduling.The International Journal of Production Research, v. 31, n. 1, p. 59-79.
Michael, R. G. & David, S. J. (1979). Computers and intractability: a guide to the theory of NP-completeness. 1979. San Francisco, LA: WH Freeman & Co.
Nagano, M. S. & Moccellin, J. V. (2002). A high quality solution constructive heuristic for flow shop sequencing. Journal of the Operational Research Society, v. 53, n. 12, p. 1374-1379.
Nagano, M. S. & Moccellin, J. V. (2008). Reducing mean flow time in permutation flow shop. Journal of the Operational Research Society, v. 59, n. 7, p. 939-945.
Nawaz, M.; Enscore, E. E. & Ham, I. (1983). A heuristic algorithm for the m-machine, n-job flow-shop sequencing problem. Omega, v. 11, n. 1, p. 91-95.
Palmer, D. (1965). Sequencing jobs through a multi-stage process in the minimum total time – A quick method of obtaining a near optimum. Operational Research Quarterly, v. 16, n. 1, p.101-107.
Pan, C. H. (1997). A study of integer programming formulations for scheduling problems. International Journal of Systems Science v. 28, p. 33–41.
Pan, Q. K. & Ruiz, R. (2013). A comprehensive review and evaluation of permutation flowshop heuristics to minimize flowtime. Computers & Operations Research, v. 40, n.1, p. 117-128.
Pinedo, M. (1995). Scheduling: theory, algorithms, and systems. 2 ed. New Jersey: Prentic-Hall.
Rad, S. F.; Ruiz, R. & Boroojerdian, N. (2009). New high performing heuristics for minimizing makespan in permutation flowshops. Omega, v. 37, n. 2, p. 331-345.
Raiendran, C. & Chaudhuri, D. (1991). A flowshop scheduling algorithm to minimize total flowtime. Journal of the Operations Research Society of Japan, v. 34, n. 1, p. 28-46.
Rajendran, C. & Ziegler, H. (1997). An efficient heuristic for scheduling in a flowshop to minimize total weighted flowtime of jobs. European Journal of Operational Research, v. 103, n. 1, p. 129-138.
Ribas, I.; Companys, R. & Tort-Martorell, X. (2010). Comparing three-step heuristics for the permutation flow shop problem. Computers & Operations Research, v. 37, n. 12, p. 2062-2070.
Ruiz, R. & Maroto, C. (2005). A comprehensive review and evaluation of permutation flowshop heuristics. European Journal of Operational Research, v. 165, n. 2, p. 479-494.
Stafford, E. F. (1988) On the development of a mixed-integer linear programming model for the flowshop sequencing problem, Journal of the Operational Research Society, v. 39, p. 1163–1174.
Stafford, E. F; Tseng, F. T. & Gupta, J. N. D. (2005). Comparative evaluation of MILP flowshop models. Journal of the Operational Research Society 56, p. 88–101.
Vasiljevic, D. & Danilovic, M. (2015). Handling ties in heuristics for the permutation flow shop scheduling problem. Journal of Manufacturing Systems, v. 35, p. 1-9. doi:10.1016/j.jmsy.2014.11.011.
Wang, C.; Chu, C. & Proth, J. M. (1997). Heuristic approaches for n|m|F|∑Ci scheduling problems. European Journal of Operational Research, v. 96, n. 3, p. 636-644.
Widmer, M. & Hertz, A. (1989). A new heuristic method for the flow shop sequencing problem. European Journal of Operational Research, v. 41, n. 2, p. 186-193.
Woo, H. S. & Yim, D. S. (1998). A heuristic algorithm for mean flowtime objective in flowshop scheduling. Computers & Operations Research, v. 25, n. 3, p. 175-182.
Ying, K. C. & Lin, S. W. (2013). A high-performing constructive heuristic for minimizing makespan in permutation flowshops. Journal of Industrial and Production Engineering, v. 30, n. 6, p. 355-362.
Zhu, Z. & Heady, R. B. (2000). Minimizing the sum of earliness/tardiness in multimachine scheduling: a mixed integer programming approach, Computers & Industrial Engineering, v. 38, p. 297–305.